Friday, 27 November 2026

Kemp Street Bridge update

 Kemp Street Bridge, Inland Rail rebuilding update


A QUBE container freight train leaves Junee 24 Nov 2026.

The whole Inland Rail project may have been cancelled by the Federal government, but construction continues on the section south of Parkes.  The major work in the Wagga to Junee area have been the replacement of bridges, both road, and pedestrian.

The new Kemp Street bridge in Junee is the subject of this blog-post. 


Kemp Street bridge in 2023, looking south.  Included here for context

In September 2025, the Kemp Street bridge was demolished.  for more pictures of the bridge, and the demolition see blogpost
https://buildingwagga.blogspot.com/2025/10/kemp-street-bridge-changes-for-inland.html


Artist impression of the new bridge

As always, click on an image for enlargement

Bridge rebuilding in pictures

December 2025  Piling had been progressing slowly.  The eastern brick abutment retaining wall had been also removed, although the western abutment retaining wall was left in place.




August 2026   More preparation work had been completed.  The first sections of the walkway were being installed






Both sections being installed will turn the walkway 180 degrees, but still maintaining the gradual slope. 

The bridge pier pilings from December strengthened

The walkway sections delivered by semi


Inland Rail were also taking time-lapse video of the operation.  The foreground is the Junee skate park, a convenient high point for viewing.  I suspect the new walkway will also become a speedway for the skateboard crowd
September 2026

The main girders for the bridge were hoisted into position over the 96 hrs of the railway shutdown


Kyle Butler took this excellent B&W picture, posted on the Junee Bulletin Facebook page, of the girder delivery truck and dolly, with erecting crane beyond

By the time I got there in Sunday, the extended jib had been removed off the crane



First girder over the last span





New western bridge abutment - concrete.

The original bridge western brick abutment still standing underneath the new spans.  The difference in height with the new bridge deck is substantial. 






The 6 girders per span are easy to count










There have been 2 houses removed on the eastern side beside the roadway.  The house that was here was transported away by truck for a new life.  The gap gives a view of the new concrete retaining wall, and a glimpse of the walkway only span 

The roadway approach on the eastern side.  


Walkway girders 

The extension jib was again attached to the crane for the walkway girder lifts

Before the last walkway girder attached to the new bridge



The new walkway in place



Concrete work on the bridge deck continues. 

October 2026
The next stage was to build up the land for the new roadway.  A large mountain of fill had been piled up on a nearby unused sports park over the last year, and a shuttle of dump trucks then transfering the fill to its final location

November 2026

Sunday Nov 15th, I was able to photograph the new work from public accessable areas without workers being suspicious of someone with a camera.

New bridge abutment on eastern side

The walkway attaches to the top of the new eastern pier.





Eastern side roadway ramp retaining wall


November 22, a container train approaches the new bridge

The extra height of the bridge can be asertained by looking at this container train.

Plenty of clearance for double stacking containers.  




The new bridge was supposed to be completed in 18 months (March 2027), but the latest advice is that it will be finished in August 2027 - 5 months later than originally advised.   Cannot come too soon.  The freight train (photo at the begining of this blog post) was moving at just 5kph due to the standard of the Junee yard tracks. The train was about 1km long - so the level crossing in town was blocked for around 12 minutes.

Conclusion
 
I find it interesting to see how things are done in the real world, and how taxpayer money is spent. It seems a lot of effort for double stacking, particular as the double stack route will no longer extend to Brisbane.  The eventual double stack route from Melbourne to Perth via Parkes is considerably longer than the alternate Overland route, although the clearances on the Overland will only allow single stacking.  There is a hope that the Inland Rail project may be restarted at some point, with perhaps the route to Gladstone chosen over Brisbane avoiding a lot of expensive tunnelling.  

Enough of my postering.  Until next time, build a model (or two)